JAXPORT Paving Dispute

In 2016, BCLG settled a high-profile dispute on behalf of the Jacksonville Port Authority (JAXPORT) over defective pavement design at the Dames Point Marine Terminal, negotiating a $10.25M settlement from a contractor and two engineering firms after nearly two and a half years of litigation. Prior to settlement of the case, the Bachara-led legal team conducted more than 100 days of depositions, analyzed more than 1.2 million documents and prepared 2,300 exhibits for trial. Due to the technical complexity of the subject matter, experts for the case were retained from as far away as the U.K., and the mediator who assisted with the settlement was from San Francisco. As a result of BCLG’s efforts, JAXPORT recovered a significant portion of its damage and avoided the heavy expense of a long and complicated trial. The Bachara Group took over as lead trial counsel for the suit at the request of the City of Jacksonville’s Office of General Counsel in March 2013. For further details, click here.

Design/Build Contractor Defense

Defended a design/build contractor against claims by a hospital that their HVAC system was under-designed. Following a three-week bench trial, the federal court determined that the contractor had in fact provided an adequate and proper design, and had neither breached the contract nor fallen below the standard of care for engineering design. For a link to the final judgment, click here.

Oceanfront Resort Owner

Represented an oceanfront resort owner against a contractor for the defective installation of concrete roof tiles. Following two days of hearings, the arbitrator determined that the roof was incorrectly installed and the contractor was responsible for $2.18 million in damages. For a link to the arbitrator’s award, click here.

Environmental & Infrastructure Contractor Defense

Defended a nationally-recognized environmental and infrastructure contractor in a construction defect claim involving a complicated drainage system installed at an environmental waste disposal site.

State University Conflict Resolution

Successfully resolved a state university’s claims against a general contractor, surety and architecture firm for construction and design defects related to design and construction of a building envelope system.

Healthcare Facility Conflict Resolution

Successfully resolved a design professional’s claim related to the design of a fire retardant system in a health care facility, as well as related delay claims brought by the contractor.

Contrator's DOT Bid Protest

Successfully resolved a contractor’s bid protest involving a Department of Transportation environmental services contract brought in the Florida Division of Administrative Hearings.

Road Contractor Bid

Defended the apparent lowest bid of a road contractor for approximately $12.5 million worth of road construction and repairs. The disappointed second-lowest bidder filed a protest asserting that the calculation of the bids was “incorrectly analyzed” and if analyzed “correctly,” would have resulted in the contract being awarded to them. Following public hearings before a hearing officer and the county commission, our client was awarded the project despite vigorous opposition and significant efforts by the second-lowest bidder to sway votes in its favor through political influence.